A set of construction and installation works on the modernization of 6 kV and 0.4 kV cable system important for the safety of the generating unit No.2 of the separate division "Rivne Nuclear Power Plant" with the following works:
- dismantling of reinforced concrete pavement of access roads with a volume of 250 m³,
- installation of metal cable structures,
- installation of 6kV and 0.4kV cable lines with the use of APvEoVng 3x150/70, APvEoVng 3x240/70, AVVGng 4x185 cables with a total length of more than 7,000 m,
- installation of 60 Raychem cable sleeves.