The Company Art-Energo develops reliable and comprehensive solar energy solutions. We offer comprehensive implementation of solar power plants construction projects for enterprises, shopping and entertainment centers, office spaces, educational institutions, and hospitals.
What will a company get from its own solar power plant?
THE IDEA IS SIMPLE: a solar power plant generates electricity for the company's own needs during daylight hours. When there is not enough "solar energy", the difference is automatically covered from the general network.
A license is not required for a solar power plant that generates electricity for own consumption, and, as a result, time required for the implementation of such a project is 1-2 months, and a company starts saving money from the first minute of the launch of such a plant.
Payback period of such a plant depends on the current electricity tariff for enterprises in Ukraine. Taking into account electricity tariffs for legal entities in 2021, set by the National Commission for State Regulation of Energy and Public Utilities, the estimated payback period of such plants is less than 6 years.
If we take into account the further probable increase of electricity tariffs for enterprises, the payback period of such projects will decrease proportionally.
Art-Energo builds "turnkey" alternative energy facilities, which are a form of an integrated system of responsibility for the facility, which includes all stages of work. This approach makes it possible to minimize the costs and time necessary for the construction of energy facilities, as the design and construction processes are performed in the optimal mode.
We offer a comprehensive implementation of solar power plant construction projects with a base cost of €895/kW with VAT.
Example. 1,000 kW solar power plant
Construction cost = 895 € * 1,000 kW = € 895,000
Annual generation of energy by a solar power plant = 1,000 kW * 1,150 hours/year = 1,150,000 kW
Consumption savings per year = 1,150,000кkWh * 0.085€ = 97,750€
- ease of operation
solar power plants do not require constant maintenance. You only need to perform scheduled maintenance every 6-12 months. Only in places where there is heavy pollution (near quarries, field roads with high traffic flows, etc.) you should additionally perform regular cleaning of solar panels
- sustainability
Of all the types of "green" energy, solar energy is the most affordable. Installation of a solar power plant for own consumption is a great opportunity to give up electricity generated by thermal power stations and to reduce СО₂ emissions. In addition, solar power plants have a number of other advantages in terms of sustainability, namely:
The technology of solar panel production does not involve the use of environmentally hazardous substances;
Operation of a solar power plant is not accompanied by harmful emissions into the atmosphere, or noise;
During the construction of a ground power plant, fertile soil layer is not damaged.
- savings
By installing a solar power plant for your own needs, you will be able to save up to 50% of the cost of expensive electricity from external power networks in a year, by replacing it with cheap solar electricity. If you have nominal consumption during daylight hours, a solar power plant will be able to cover up to 70-100% of the company's electricity needs in spring and summer and 20-40% in autumn and winter. When installing a rooftop solar power station, the roof becomes less heated, which allows you to save money on building cooling.
- durability
Most solar panel manufacturers give a 25-year warranty on their products, while the efficiency of solar panels is reduced by only 15% in 25 years. The average service life is more than 50 years.
Solar Power plant by ART-ENERGO
Pos. |
Name of the object of electric power industry |
Location of the electric power industry |
Title and type of equipment |
Quantity, pc |
Installed power, kW |
Type of fuel |
Own |
1 |
Roof Solar Power Plant (І stage) |
20a, T.Dorosha st., village Malechiv, Lviv area, 03833 |
PV Module Solar impulse YSUN-270P-60, peak power 270W | 3705 |
1000,35 |
Energy of sun |
Rent |
Inverter Schneider Electric Conext CL-60E, Ph=66kW | 14 |
924,00 |
--- | ||||
2 |
Roof Solar Power Plant (ІІ stage) |
20a, T.Dorosha st., village Malechiv, Lviv area, 03833 |
PV Module JA SOLAR JAP60S01-270/SC, peak power 270W |
3705 |
1000,35 |
Energy of sun |
Rent |
Inverter Schneider Electric Conext CL-60E, Ph=66kW | 14 |
924,00 |
--- | ||||
3 |
Roof Solar Power Plant |
21, Sknylivska st., Pustomyty district, Lviv area, 81130 |
PV Module , peak power 275W | 240 | 66,00 | Energy of sun | Rent |
Inverter Schneider Electric Conext CL20000E, Ph=20kW | 3 | 60,00 | --- | ||||
4 |
Roof Solar Power Plant |
village Zapytiv, Kamianka- Buzk district, Lviv area, 80461 |
PV Module, peak power 275W | 1818 |
499,95 |
Energy of sun |
Rent |
Inverter Schneider Electric Conext CL20000E, Ph=20kW | 3 | 60,00 | --- | ||||
Inverter Schneider Electric Conext CL-60E, Ph=66kW | 6 | 396,00 | --- | ||||
5 |
Roof Solar Power Plant |
10, Plastova st., Lviv, 79056 |
PV Module, peak power 270W | 3630 | 980,10 | Energy of sun | Rent |
Inverter Schneider Electric Conext CL-60E, Ph=66kW | 13 | 858,00 | --- | ||||
6 |
Ground Solar Power Plant "VOROTSIV" |
village Vorotsiv, Yavorivskii district, Lviv area, 81086 |
PV Module TSM-275 PE05A, peak power 275W | 11640 | 3201 | Energy of sun |
Own |
Inverter Schneider Electric Conext CL-125PV, Ph=125kW | 22 | 2750 | --- | ||||
7 |
Ground Solar Power Plant "VOROTSIV-2" |
village Vorotsiv, Yavorivskii district, Lviv area, 81086 (cadastral number 4625882900:04:001:1416) |
PV Module, TrinaSolar TSM-375DE08M(II), Ph=375W | 19 | 7,125 |
Energy of sun |
Own |
PV Module, TrinaSolar TSM-370DE08M(II), Ph=370W | 1917 | 709,29 |
Energy of sun |
||||
Inverter Kehua Tech SPI160K-B-H, Ph=160kW | 4 | 640,00 | --- | ||||
8 | Ground Solar Power Plant "VOROTSIV-3" |
village Vorotsiv, Yavorivskii district, Lviv area, 81086 (cadastral number 4625882900:04:001:1415) |
PV Module, TrinaSolar TSM-370DE08M(II), Ph=370W | 1984 | 734,08 | Energy of sun | Own |
Inverter Kehua Tech SPI160K-B-H, Ph=160kW | 4 | 640,00 | --- | ||||
Total |
8198,245 |