PE “Nordik”

Back

A package of works relating to external electric power supply to Sambir Solar Power Plant, one of the first alternative energy facilities in Western Ukraine, located in the village of Ralivka, Sambir district, Lviv region, with a capacity of 5 MW and connecting the power generating units to the networks of SRSA "Lviv Railway":

  • design
  • supply of equipment
  • construction of a 10 kV cable line with a total length of 1 km
  • six-core АПвЕгаП (NA2XSF(L)2Y)-10 1x240/70 from the Sambir traction substation to the Sambir solar power plant, including a perforation under the bed of the river Dniester
  • installation of 4 prefabricated transformer substations with 1,000 kVA power transformers
  • replacement of oil circuit breakers with BB/TEL vacuum circuit breakers with an adaptation kit
  • installation of relay protection and automation circuits
  • replacement of two 6 kV cable lines with ААБЛ-10 3x120 mm2 - L-400M at the ЕЧЕ-23 substation of SRSA "Lviv Railway"
  • installation and adjustment of ASCAEP
  • preparation of technical documentation for the client to obtain a licence from the National Energy and Utilities Regulatory Commission of Ukraine to generate power under a "green tariff"
  • commissioning
  • putting into operation